(adds trash system)
(→‎Basement: adds list first-pass)
Line 46: Line 46:
==Basement==
==Basement==
(kitchen + fnb + mpm + baps + bhc + omp + ?)
(kitchen + fnb + mpm + baps + bhc + omp + ?)
* Replace all missing fire insulation ceiling tiles
* Tie up loose ends, any hanging fixtures, trim, etc needs to be re-affixed.


===Kitchen===
===Kitchen===
Line 58: Line 61:
===Library===
===Library===
* Move all shelves and books up into the ballroom
* Move all shelves and books up into the ballroom
===Print Shop===
* Preliminary ventilation (check existing vents)
** They're currently using non-toxic (green) solvents, low-odor, low-impact
* Extensive ventilation for future printing purposes
** For operating the offset printing press (later).
* ADA accessibility for walkways.
* Safety demarcations for presses, etc
* Keep back entrance to sudo clear.
* Lighting improvements
* Electrical audit
===Middle Rooms===
* Inspect past water leakages, damage
* Sound-proofing
* Electrical audit
*
=== Basement General ===
* Needs electrical outlets very badly (e.g. for meeting space)
===Blackhole Labs===
* Walls, doors
* Insulation
* HVAC, especially for ventilation
* Repurposing of raised platform?
* Electrical audit


==Bocce Ball Court==
==Bocce Ball Court==

Revision as of 23:31, 8 February 2015

This page exists as a living checklist for all the tasks we need to get done for Omni to be "ready" ;)

Once a task is completed:

  • It should be crossed out
  • Incomplete tasks are not crossed out yet!

Enjoy.

Ballroom

See full documentation on Ballroom-readiness page.

Code-compliance

Cosmetic Work

A/V and Stage Production

Basement

(kitchen + fnb + mpm + baps + bhc + omp + ?)

  • Replace all missing fire insulation ceiling tiles
  • Tie up loose ends, any hanging fixtures, trim, etc needs to be re-affixed.

Kitchen

  • Expand walls
  • Seal off pantry (give to black hole collective labs)
  • Install dish washer
  • Finish fixing up stoves & overhead
  • Build closet for mop sink and water heater
  • Coat / seal floor

Library

  • Move all shelves and books up into the ballroom

Print Shop

  • Preliminary ventilation (check existing vents)
    • They're currently using non-toxic (green) solvents, low-odor, low-impact
  • Extensive ventilation for future printing purposes
    • For operating the offset printing press (later).
  • ADA accessibility for walkways.
  • Safety demarcations for presses, etc
  • Keep back entrance to sudo clear.
  • Lighting improvements
  • Electrical audit

Middle Rooms

  • Inspect past water leakages, damage
  • Sound-proofing
  • Electrical audit

Basement General

  • Needs electrical outlets very badly (e.g. for meeting space)

Blackhole Labs

  • Walls, doors
  • Insulation
  • HVAC, especially for ventilation
  • Repurposing of raised platform?
  • Electrical audit

Bocce Ball Court

(sudo + ccl)

La Commune

Mezzanine

(til + tiny-room + den + kitchenette + shower + bathroom)

Disco Room

Rise Above

Bike Kitchen

Walk-in Freezer

Omni - Throughout

  • Implement new / upgraded trash system (Jenny)

Hallways and Thoroughfares

  • Remove trash cans, store somewhere not in path of travel
  • Make tape-based paths for unclear areas to maintain accessible paths free from clutter.

Questions

  1. Do all doors need to be lockable? Do any need to be electrified? Why? No ballrom doors are primary access, right?