Event:2015/06/08 Building Working Group
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Omni Commons Building Working Group meeting - Monday June 8 2015
previously
https://omnicommons.org/wiki/Event:2015/05/26_DK_Brain_Dump https://omnicommons.org/wiki/Event:2015/06/01_Building_Working_Group
South wall
- Bottom level almost finished
- Walls framed for upstairs
- put wires up today (to hold up the fiberglass)
- shot foam into cracks near the west end
- Calvin Lee is our plan checker for the city. DK waiting until he is the engineer of the day to get permit.
- Laura and Yar + whoever will go to city tomorrow to finish permit, after talking to DK. Joe will orient on plans
- Joe is leaving this Saturday for 10 days (Sat 13th - Tue 23rd)
- We should aim for 1st inspection of framing the week of the 15th
what's left?
- joe's got another 3 days of work (not thursday)
- will hopefully finish the framing for inspection
- will get the two ends of the bottom wall, by the closet & staircase
basement
- rob cut out moldy parts of the drywall. too soggy to scrub.
- temporarily patched the holes with boards - foam, wood, etc
- used a steam cleaner + borax
- framing is still deteriorated - the footer wood is rotten, crumbling
- ideally we'd replace framing if we ever get more money
- priority is to pass fire inspection so let's just cover it with drywall, will look fine
- will that be fire safe?
- joe says it wouldn't be that hard to just put cripples on the bottom
doors
- anka & dusty working on doors tomorrow
- hallway door to sudo/ccl is poorly hung. frustrating.
front door
- nothing's happening
- city didn't like our idea
- they're putting in the opener
- it's too low but we're gonna do it anyway
bathroom
- yar still hasn't treated the concrete. trying to find the bucket of stuff again.
- do we need more womens' bathrooms?
- fire doesn't care about that. whole other can of worms.
DIsco Room
- Joe finished taping drywall facing LC
- empty socket with no bulb, no globe/cover, no exposed wires up in the ladder closet thingy
hole in the west wall
- should we insulate the DR hole before closing it? tyvek? denim? might need weather proofing
- will the drywall overlap? will that look bad? we could hang a picture or a mirror over it
- entire wall of the dance floor has a U-channel, all ready for mirrors. just need to set them in & tack them. just need to find them the right height or cut them.
- should we frame it? silicone it?
- no, as long as it's closed, it's fine. screws, spackle, done.
- but the edges will look weird
- we'll figure it out tomorrow
kitchen
- meeting tomorrow with max, sophia chang (the kitchener), sal (actual cafe)
Other Reports
- laura's working through the big list piece by piece
- talk about covering more lightbulbs
- gerald wants to get LC ceiling tiles gone, but those are necessary for the cafe to operate
- laura will contact gerald to take on some of the small electrical jobs and filling in ceiling tile
- roan has other stuff going on, unable to work right now
- ballroom bathroom grafitti's getting better. more diverse. because joe is writing it.
- storage closet shelves are caving in / bowing. need to be redone.
- trash room is a mess. people aren't sorting it because not enough bins clearly labelled. laura will buy some 3-in-1 bins
priorities
upcoming milestones
- fire inspection
- usable ADA toilet
dangerous distractions
- stage projector screen