Omni Commons Building Working Group meeting - Monday June 8 2015

previously

https://omnicommons.org/wiki/Event:2015/05/26_DK_Brain_Dump https://omnicommons.org/wiki/Event:2015/06/01_Building_Working_Group

South wall

  • Bottom level almost finished
  • Walls framed for upstairs
  • put wires up today (to hold up the fiberglass)
  • shot foam into cracks near the west end
  • Calvin Lee is our plan checker for the city. DK waiting until he is the engineer of the day to get permit.
  • Laura and Yar + whoever will go to city tomorrow to finish permit, after talking to DK. Joe will orient on plans
  • Joe is leaving this Saturday for 10 days (Sat 13th - Tue 23rd)
  • We should aim for 1st inspection of framing the week of the 15th

what's left?

  • joe's got another 3 days of work (not thursday)
  • will hopefully finish the framing for inspection
  • will get the two ends of the bottom wall, by the closet & staircase

basement

  • rob cut out moldy parts of the drywall. too soggy to scrub.
  • temporarily patched the holes with boards - foam, wood, etc
  • used a steam cleaner + borax
  • framing is still deteriorated - the footer wood is rotten, crumbling
  • ideally we'd replace framing if we ever get more money
  • priority is to pass fire inspection so let's just cover it with drywall, will look fine
  • will that be fire safe?
  • joe says it wouldn't be that hard to just put cripples on the bottom

doors

  • anka & dusty working on doors tomorrow
  • hallway door to sudo/ccl is poorly hung. frustrating.

front door

  • nothing's happening
  • city didn't like our idea
  • they're putting in the opener
  • it's too low but we're gonna do it anyway

bathroom

  • yar still hasn't treated the concrete. trying to find the bucket of stuff again.
  • do we need more womens' bathrooms?
  • fire doesn't care about that. whole other can of worms.

DIsco Room

  • Joe finished taping drywall facing LC
  • empty socket with no bulb, no globe/cover, no exposed wires up in the ladder closet thingy

hole in the west wall

  • should we insulate the DR hole before closing it? tyvek? denim? might need weather proofing
  • will the drywall overlap? will that look bad? we could hang a picture or a mirror over it
  • entire wall of the dance floor has a U-channel, all ready for mirrors. just need to set them in & tack them. just need to find them the right height or cut them.
  • should we frame it? silicone it?
    • no, as long as it's closed, it's fine. screws, spackle, done.
    • but the edges will look weird
    • we'll figure it out tomorrow

kitchen

  • meeting tomorrow with max, sophia chang (the kitchener), sal (actual cafe)

Other Reports

  • laura's working through the big list piece by piece
  • talk about covering more lightbulbs
  • gerald wants to get LC ceiling tiles gone, but those are necessary for the cafe to operate
    • laura will contact gerald to take on some of the small electrical jobs and filling in ceiling tile
    • roan has other stuff going on, unable to work right now
  • ballroom bathroom grafitti's getting better. more diverse. because joe is writing it.
  • storage closet shelves are caving in / bowing. need to be redone.
  • trash room is a mess. people aren't sorting it because not enough bins clearly labelled. laura will buy some 3-in-1 bins

priorities

upcoming milestones

  • fire inspection
  • usable ADA toilet

dangerous distractions

  • stage projector screen