Difference between revisions of "Electrical"

From Omni Commons
Jump to navigation Jump to search
(jpg -> jpeg)
 
(21 intermediate revisions by 3 users not shown)
Line 1: Line 1:
This page provides a "living document" of the Omni Commons electrical system. It is not necessarily completely accurate, though it strives to be, and is always important to get updated!
This page provides a "living document" of the Omni Commons electrical system. It is not necessarily completely accurate, though it strives to be, and is always important to get updated! Also see our [[power usage]], [[floorplans]], [[Media:Panel Diagram.pdf|old breaker diagram]], and [[cancelled panels]].


6 of these panels are Federal Electric and need to be replaced ASAP: [[#Panel A|A]], [[#Panel AB|AB]], [[#Panel AD|AD]], [[#Panel AE|AE]], [[#Panel BA|BA]]
Omni's building used to have FPE Electrical panels and breakers. They have been removed and replaced with code compliant items as of October 2021.
 
Also see our page on [[power usage]]
 
== Timeline ==
 
* In 2021, Kent Cates (electrician) evaluated all our panels and wrote [https://drive.google.com/drive/u/0/folders/0B4_Q7DQvNFT-RFFCZmNQTWVMTXM a brief report] <blockquote>Inspection of Electrical System at Omni Commons - 4799 Shattuck ave - 2/5/2021. Main Electrical service is 200 amps, Copper wire Thhn. There are 12 sub panels throughout the building , Feeder wires are Copper THWN and THHN wire. Found 1 small panel that had Aluminum wire. Panel types were General Electric, Federal Pacific, Siemons, Industrial Electrical. Sub Feed wiring is in Conduit and MCC, wire type is Copper Thhn, THWN and some cloth covered  ires. No Aluminum wire was found. There was No Knob and Tube wiring found in the building.</blockquote>
 
==Panels==


* '''[[#Main Panel|Main Panel]]''' (in ANV office, room E of rear [48th St] exit)
* '''[[#Main Panel|Main Panel]]''' (in ANV office, room E of rear [48th St] exit)
** '''[[#Panel A|Panel A]]''' (adjacent to main in ANV office)
** '''[[#Panel A|Panel A]]''' (adjacent to main in ANV office)
*** '''[[#Panel AA|Panel AA]]''' (in ANV office, on E wall adjacent to Entrance Hall)
*** '''[[#Panel AB|Panel AB]]''' (in basement next to N staircase)
*** '''[[#Panel AB|Panel AB]]''' (in basement next to N staircase)
*** '''[[#Panel AC|Panel AC]]''' (in basement NW Kitchen Pantry, on E wall)
*** '''[[#Panel AD|Panel AD]]''' (located upstage left in N corner of W wall of ballroom)
*** '''[[#Panel AD|Panel AD]]''' (located upstage left in N corner of W wall of ballroom)
**** '''[[#Panel ADA|Panel ADA]]''' (in shower room on E wall)
*** '''[[#Panel AE|Panel AE]]''' (located in storage room S of stage in N corner of W wall of ballroom)
*** '''[[#Panel AE|Panel AE]]''' (located in storage room S of stage in N corner of W wall of ballroom)
** '''[[#Panel B|Panel B]]''' (in Crow's Nest above stage in ballroom)
** '''[[#Panel B|Panel B]]''' (in Crow's Nest above stage in ballroom)
*** '''[[#Panel BA|Panel BA]]''' (in rear ballroom balcony near S wall)
*** '''[[#Panel BA|Panel BA]]''' (in rear ballroom balcony near S wall)
**** '''[[#Panel BAA|Panel BAA]]''' (on N wall of classroom between ballroom and Entrance Hall)
***** '''[[#Panel BAAA|Panel BAAA]]''' (behind Entrance Hall counter on S wall)
***** '''[[#Panel BAAA|Panel BAAA]]''' (behind Entrance Hall counter on S wall)
** '''[[#Panel C|Panel C]]''' (in Disco Room at base of ladder to DJ booth)
** '''[[#Panel C|Panel C]]''' (in Disco Room at base of ladder to DJ booth)
** '''[[#Panel D|Panel D]]''' (in ANV office on E wall shared with Entrance Hall)
** '''[[#Panel D|Panel D]]''' (in ANV office on E wall shared with Entrance Hall)
* '''CCL Panel''' - (Located next to door into CCL / sudo room area) - Apparently not yet documented here?
* '''CCL Panel''' - (Located next to door into CCL / sudo room area) - Apparently not yet documented here?
 
__NOTOC__
'''X''' = Disconnected


===Main Panel===
===Main Panel===
Line 73: Line 59:
[[File:Panel-A-2021-04-29.jpeg|right|thumb|Panel A open]]
[[File:Panel-A-2021-04-29.jpeg|right|thumb|Panel A open]]


'''''This panel is Federal Electric and needs to be replaced ASAP.'''''
'''''This is a picture of Omni's former panel that was Federal Electric and has since been replaced.'''''


200amps
200amps
Line 90: Line 76:
| 4 || 24 ||
| 4 || 24 ||
|-
|-
|rowspan="4"| ? [[#Panel AC|Panel AC]]
|rowspan="4"| [[#Panel AC|Panel AC]] (breaker is removed until kitchen renovated)
| 5 || 25
| 5 || 25
|rowspan="4"| [[#Panel AD|Panel AD]]
|rowspan="4"| [[#Panel AD|Panel AD]]
Line 109: Line 95:
| Hood over oven in upstairs<br/> kitchenette (cafe mezzanine) /<br/> W Wall Kitchenette Outlet (R of sink) /<br/> W wall kichenette outlet (Above oven in alcove) || 12 || 32 ||
| Hood over oven in upstairs<br/> kitchenette (cafe mezzanine) /<br/> W Wall Kitchenette Outlet (R of sink) /<br/> W wall kichenette outlet (Above oven in alcove) || 12 || 32 ||
|-
|-
| || 13 || 33 ||
| CCL storage rooms lights || 13 || 33 ||
|-
|-
|  || 14 || 34 ||
|  || 14 || 34 ||
|-
|-
| || 15 || 35 ||  
| switch on wall of disco room || 15 || 35 ||  
|-
|-
|  || 16 || 36 || X
|  || 16 || 36 || X
|-
|-
| || 17 || 37 || Blue Classroom S wall outlets
| Right switch disco room fans || 17 || 37 || Blue Classroom S wall outlets
|-
|-
| 2 TIL Office Lights (upstairs) /<br/> Front Door Exit Sign /<br/>Two Lights on Beam at entrance || 18 || 38 ||  
| 2 TIL Office Lights (upstairs) /<br/> Front Door Exit Sign /<br/>Two Lights on Beam at entrance || 18 || 38 ||  
Line 124: Line 110:
|-
|-
| Upstairs kitchenette (cafe mezzanine) S wall outlets /<br/> W Wall Kitchenette Outlet (L of sink) /<br/> N wall kitchenette outlets (at entrance) /<br/> Outlets under bar on S Wall of Disco Room <br/>near S Wal of Kitchenette || 20 || 40 ||  
| Upstairs kitchenette (cafe mezzanine) S wall outlets /<br/> W Wall Kitchenette Outlet (L of sink) /<br/> N wall kitchenette outlets (at entrance) /<br/> Outlets under bar on S Wall of Disco Room <br/>near S Wal of Kitchenette || 20 || 40 ||  
|} <br clear=all>
===Panel AA===
[[File:Panel-AA-2021-04-29.jpeg|right|thumb|Panel AA]]
This panel is a mystery to us. We could not identify any use for most of the breakers, other than #9. I suspect it may have fed the former bar area fridges, appliances & outlets which were demolished in 2015. Perhaps the overhead lights as well.
'''''This Federal Electric panel HAS BEEN REMOVED and its circuits moved to [[#Panel D|Panel D]]'''''
{| class="wikitable" style="text-align: center;"
|-
! Label -> !! Breaker # !! Breaker # !! <- Label
|-
|
| 6 || 12
|
|-
|
| 5 || 11
|
|-
|
| 4 || 10
|
|-
|
| 3 || 9
| wheelchair bathroom light & outlet, exit light at the west edge of entrance hall (exit to the hallway), secure storage & cleaning closet
|-
|
| 2 || 8
|
|-
|
| 1 || 7
|
|} <br clear=all>
|} <br clear=all>


Line 165: Line 115:
[[File:Panel-ab.jpg|right|thumb|Panel AB]]
[[File:Panel-ab.jpg|right|thumb|Panel AB]]


'''''This panel is Federal Electric and needs to be replaced ASAP.'''''
'''''This is a picture of Omni's former panel that was Federal Electric and has since been replaced.'''''
 
In 2019 we added another circuit to this box to power lights & outlets in the secure storage closet above it. In the confusion, something may have been switched around. Liblens briefly lost power. Needs to be re-assessed and re-labeled.<br>
<i>"quotes" are from [[Media:Panel Diagram.pdf|old breaker diagram]] re: "DOWNSTAIRS DINING AREA PANEL"</i>


In 2019 we added another circuit to this box to power lights & outlets in the secure storage closet above it. In the confusion, something may have been switched around. Liblens briefly lost power. Needs to be re-assessed and re-labeled.
7/8 is one breaker, see image.


{| class="wikitable" style="text-align: center;"
{| class="wikitable" style="text-align: center;"
Line 173: Line 126:
! Label -> !! Breaker # !! Breaker # !! <- Label
! Label -> !! Breaker # !! Breaker # !! <- Label
|-
|-
|rowspan="2"| 20A basement furnace?
| 20A basement furnace? "Blank"
| 8 || 16
| 8 || 16
| 15A
| 15A "Blank" (nothing connected)
|-
|-
| "Dining Room Furnace"
| 7 || 15
| 7 || 15
| 15A Liberated Lens, other small basement rooms & adjacent outlets.  
| 15A Liberated Lens, other small basement rooms & adjacent outlets.  
|-
|-
| 15A kitchen & pantry lights
| 15A pantry & "Kitchen Lights"
| 6 || 14
| 6 || 14
| 15A
| 15A
Line 186: Line 140:
| 20A
| 20A
| 5 || 13
| 5 || 13
| 15A large basement meeting room - most outlets except on south wall
| 15A large basement meeting room - most outlets except on south wall "Receptacle"
|-
|-
| 20A
| 20A "Stage Receptacle"
| 4 || 12
| 4 || 12
| 15A lights in large basement meeting room & rear basement hallway
| 15A lights in large basement meeting room & rear basement hallway
|-
|-
| 20A Ballroom Furnace
| 20A "Ball"room Furnace
| 3 || 11
| 3 || 11
| 15A
| 15A "Office lights"
|-
|-
| 15A Entrance Hall<br/>Furnace
| 15A Entrance Hall<br/>"Lower Bar Furnace"
| 2 || 10
| 2 || 10
| 15A basement flourescent lights
| 15A basement flourescent "Lights"
|-
|-
| 30A kitchen outlets, fridges
| 30A kitchen outlets, fridges "Refrigerator"
| 1 || 9
| 1 || 9
| 15A basement flourescent lights
| 15A basement flourescent "Lights"
|} <br clear=all>
 
===Panel AC===
[[File:Panel-ac.jpg|right|thumb|Panel AC]]
'''''This panel is Federal Electric but is no longer receiving power.  It will be replaced with the kitchen remodeling'''''
 
this panel is located on the East wall of the West pantry of the basement kitchen.
 
its feed was a 40A/40A double breaker from Panel A WHICH HAS BEEN REMOVED
 
this panel only powered the kitchen stove hood fan & light before this panel was then disconnected at its feed.
 
{| class="wikitable" style="text-align: center;"
|-
! info !! Breaker #
|-
| nothing || 4
|-
| nothing? || 3
|-
| nothing? || 2
|-
| hood fan & light || 1
|} <br clear=all>
|} <br clear=all>


Line 264: Line 195:
|} <br clear=all>
|} <br clear=all>


===Panel ADA===
===Panel AE===
[[File:Panel-ada.jpg|right|thumb|Panel ADA]]
[[File:Panel_AE_20221214.jpg|right|thumb|Panel AE]]


This panel is located upstairs in the "shower room" which also used to house a hot tub and laundry machines.
Observations 2022/12/14:
* Left column, top down
* 15
* 15
* 20/20 exit sign upstairs
* 20
* 20 socket on 1fl ceiling near southeast staircase


{| class="wikitable" style="text-align: center;"
* Right column, top down
|-
* 20
! Label -> !! Breaker #
* 20 exit east side of ballroom
|-
* 15
| Former Hot Hub || 1
* 15
|} <br clear=all>
* 15 ballroom string lights (draped around)


===Panel AE===
Old labels:
[[File:Panel-ae.jpg|right|thumb|Panel AE]]
 
'''''This panel is Federal Electric and needs to be replaced ASAP.'''''
{| class="wikitable" style="text-align: center;"
{| class="wikitable" style="text-align: center;"
|-
|-
Line 334: Line 268:
[[File:Panel-ba.jpg|right|thumb|Panel BA]]
[[File:Panel-ba.jpg|right|thumb|Panel BA]]


'''''This panel is Federal Electric and needs to be replaced ASAP.'''''
'''''This is a picture of Omni's former panel that was Federal Electric and has since been replaced.'''''


{| class="wikitable" style="text-align: center;"
{| class="wikitable" style="text-align: center;"
Line 348: Line 282:
|-
|-
| Aux #4 || 7 || 8
| Aux #4 || 7 || 8
|rowspan="2"| [[#Panel BAAA|Panel BAAA]] (in entrance hall)<br>via [[#Panel BAA|Panel BAA]] (in Office #1)
|rowspan="2"| [[#Panel BAAA|Panel BAAA]] (in entrance hall)
|-
|-
| X || 9 || 10
| X || 9 || 10
Line 358: Line 292:
| Aux #5 || 15 || 16 || Aux #3
| Aux #5 || 15 || 16 || Aux #3
|} <br clear=all>
|} <br clear=all>
===Panel BAA===
[[File:Panel BAA after cancel.jpg|right|thumb|Panel BAA]]
'''''This panel HAD Federal Electric breakers BUT is now only a junction box, and is no longer hazardous.'''''
This cabinet is simply a junction box for a feed coming from [[#Panel BA|Panel BA]]<br/>in ballroom mezzanine and going to [[#Panel BAAA|Panel BAAA]]<br/>in Entrance Hall.<br>
A screw prevents the door from being opened, and there is nothing to see in there.
<br clear=all>


===Panel BAAA===
===Panel BAAA===
Line 391: Line 316:


I couldn't find this panel to take a picture --yar
I couldn't find this panel to take a picture --yar
This panel is camera shy.
Located in Disco Room at base of ladder to DJ booth


===Panel D===
===Panel D===
Line 398: Line 326:
100 amps <br clear=all>
100 amps <br clear=all>


There is a wire in this box that comes from the other side of the wall, in a junction box 5' off the ground covered with a [https://www.google.com/search?q=2+gang+Plastic+Blank+Wall+Plate| 2 gang Plastic Blank Wall Plate] which is joined to wires assumed to go to outlets lower on that wall.  But since we didn't see the expected result when we hooked it up, it's not connected right now.  Also there are no available circuits left in this box.  That wire is labeled inside this panel.
This is a picture of something that has since been fixed.
 
===Fan Panel===
 
[[File:Fan-panel-downstairs.jpeg|right|thumb|single mystery breaker downstairs]]
 
It says "exhaust fan", but does not have power coming in, and serves no known purpose.  Breaker was removed and front panel capped off with a metal plate.  Feed wires inside are capped off.  (needs updated picture) <br clear=all>
 
==Floorplans==
 
<gallery mode="nolines">
File:Panel Tree Diagram|{Placeholder}
File:Annotated Floorplan|{Placeholder}
File:4799 Shattuck floorplan Set 3-vectorized-AllFloors-v2-PDF.pdf|Unlabeled Floorplan (basis)
</gallery>
 
==Documentation Protocol==
 
Any building's electrical system is intended to serve the needs of the users of the building in a safe manner. However, we operate within constraints such as the historical developments of the electrical system, regulations, best practices, etc. In order to reduce ambiguity and risk, we must use a consistent documentation protocol throughout the system to understand and share knowledge of historical, current, and future uses.
 
===Naming Convention===
 
* Label the main electrical panel as '''"MAIN"'''
* Label the direct sub-panels of the main panel with a letter, e.g. '''"A"''', '''"B"'''.
* Label each sub-panel that is connected to a first-tier sub-panel of the main panel.
** '''"origin panel letter"''' + '''"sub-panel letter"''' + ... (for each sub-panel add another letter) ...
*** e.g. '''"AA"''' for the first sub-panel from panel '''"A"'''
*** e.g. '''"AAB"''' for the second sub-panel attached to panel '''"AA"'''
* For each circuit, label each outlet, switch, and load with:
** the appropriate sub-panel name (described above) + '''"breaker number"'''
*** e.g. All the outlets in one room that are on the same circuit should be labeled '''"CA4"''' meaning the circuit is on breaker '''4''' on panel '''CA''', which is the first panel originating from panel '''C''' that connects to the '''Main''' panel.
** the draw on the curcuit
*** e.g. '''20 amps'''
 
Here is the OLD [[Media:Panel Diagram.pdf|breaker panel diagram]]
 
===Protocol===
 
* We are especially (not exclusively) updating our electrical system documentation on a room-by-room basis.
* As you work throughout Omni Commons, you should '''only''' use the system described above to map the electrical system.
* All other systems will be overridden.
* You can print this page and the building floorplans above in order to document the labeling you make on the actual outlets, panels, etc.
** After labeling and writing on the printed building floorplan, deliver it to any member of the [[Building Construction and Maintenance Working Group|Building Working Group]].


[[Category:Building]]
[[Category:Building]]

Latest revision as of 04:04, 28 March 2024

This page provides a "living document" of the Omni Commons electrical system. It is not necessarily completely accurate, though it strives to be, and is always important to get updated! Also see our power usage, floorplans, old breaker diagram, and cancelled panels.

Omni's building used to have FPE Electrical panels and breakers. They have been removed and replaced with code compliant items as of October 2021.

  • Main Panel (in ANV office, room E of rear [48th St] exit)
    • Panel A (adjacent to main in ANV office)
      • Panel AB (in basement next to N staircase)
      • Panel AD (located upstage left in N corner of W wall of ballroom)
      • Panel AE (located in storage room S of stage in N corner of W wall of ballroom)
    • Panel B (in Crow's Nest above stage in ballroom)
      • Panel BA (in rear ballroom balcony near S wall)
          • Panel BAAA (behind Entrance Hall counter on S wall)
    • Panel C (in Disco Room at base of ladder to DJ booth)
    • Panel D (in ANV office on E wall shared with Entrance Hall)
  • CCL Panel - (Located next to door into CCL / sudo room area) - Apparently not yet documented here?


Main Panel

Omni's main electrical panel
Label -> Breaker # Breaker # <- Label
Panel B & Panel D 200amps 1 2
3 4
Panel A 200amps 5 6
7 8
X 9 10 Panel C 100amps
11 12
Storage #5 / Trash Room 13 14 n/a
15 16 n/a
Storage #5 / Trash Room 17 18 n/a
Counter Culture Labs
(CCL) Closet
19 20 n/a
21 22 n/a
n/a 23 24 n/a


Panel A

Panel A
Panel A open

This is a picture of Omni's former panel that was Federal Electric and has since been replaced.

200amps

Label -> Breaker # Breaker # <- Label
1 21 Panel AE
2 22
Panel AB 3 23
4 24
Panel AC (breaker is removed until kitchen renovated) 5 25 Panel AD
6 26
7 27
8 28
9 29  
Upstairs (cafe mezzanine) kitchen light /
Upstairs (cafe mezzanine) bathroom lights /
Exit Sign at top of W cafe mezzanine staircase
10 30 Sudo Room outlets
on South Wall
Outlets along north wall of entrance hall 11 31
Hood over oven in upstairs
kitchenette (cafe mezzanine) /
W Wall Kitchenette Outlet (R of sink) /
W wall kichenette outlet (Above oven in alcove)
12 32
CCL storage rooms lights 13 33
14 34
switch on wall of disco room 15 35
16 36 X
Right switch disco room fans 17 37 Blue Classroom S wall outlets
2 TIL Office Lights (upstairs) /
Front Door Exit Sign /
Two Lights on Beam at entrance
18 38
Light fixture and outlets in
Blue Classroom alcove on N wall
19 39
Upstairs kitchenette (cafe mezzanine) S wall outlets /
W Wall Kitchenette Outlet (L of sink) /
N wall kitchenette outlets (at entrance) /
Outlets under bar on S Wall of Disco Room
near S Wal of Kitchenette
20 40


Panel AB

Panel AB

This is a picture of Omni's former panel that was Federal Electric and has since been replaced.

In 2019 we added another circuit to this box to power lights & outlets in the secure storage closet above it. In the confusion, something may have been switched around. Liblens briefly lost power. Needs to be re-assessed and re-labeled.
"quotes" are from old breaker diagram re: "DOWNSTAIRS DINING AREA PANEL"

7/8 is one breaker, see image.

Label -> Breaker # Breaker # <- Label
20A basement furnace? "Blank" 8 16 15A "Blank" (nothing connected)
"Dining Room Furnace" 7 15 15A Liberated Lens, other small basement rooms & adjacent outlets.
15A pantry & "Kitchen Lights" 6 14 15A
20A 5 13 15A large basement meeting room - most outlets except on south wall "Receptacle"
20A "Stage Receptacle" 4 12 15A lights in large basement meeting room & rear basement hallway
20A "Ball"room Furnace 3 11 15A "Office lights"
15A Entrance Hall
"Lower Bar Furnace"
2 10 15A basement flourescent "Lights"
30A kitchen outlets, fridges "Refrigerator" 1 9 15A basement flourescent "Lights"


Panel AD

Panel AD

Located upstage left (facing the ballroom) in North corner of West wall of stage

Breaker # Label
1 GFI outlet (used for
screen printing sink in
Mezzanine Shower Room)
2 Vanity lights above stage
Stage Left Ballroom Floor Outlets
3 Upstage Center outlet

& Stage Left Outlet

SE Ballroom (Library) Bathroom Lights

& Exit Light

4 Stage Right Ballroom Floor Outlets

& Stage Right Outlets

5 NW Ballroom (piano) Bathroom Light

& NW Bathroom Hallway Light

6 Crow's Nest Interior light/fan

& SW Ballroom Staircase Light
& Ballroom Mop Closet Light
& Lights beneath Ballroom Mezzanine
& AV Room Lights


Panel AE

Panel AE

Observations 2022/12/14:

  • Left column, top down
  • 15
  • 15
  • 20/20 exit sign upstairs
  • 20
  • 20 socket on 1fl ceiling near southeast staircase
  • Right column, top down
  • 20
  • 20 exit east side of ballroom
  • 15
  • 15
  • 15 ballroom string lights (draped around)

Old labels:

Label -> Breaker # Breaker # <- Label
Stage left floor outlet/s 1 2 Ballroom Under Bar
Outlet #2 (from L)
Stage right floor outlet/s 3 4 Ballroom Under Bar
Outlet #1 (from L)
Ballroom Shattuck Entrance's Exit Signs (3)
Ballroom Under Bar
Outlet #3 (from L)
5 6 Stage Storage Room (office #3) Outlets
Ballroom Under Bar
Outlet #4 (from L)
7 8 X
Ballroom Balcony S Wall Lights
& SW Staircase Exit Signs
& SE Staircase lights / exit signs
& SW Ballroom wall outlets
9 10 X
X 11 12 X


Panel B

Panel B

100amps

Label -> Breaker # Breaker # <- Label
X 1 2 X
X 3 4 X
X 5 6 Basement Vent
X 7 8
Panel BA
(Ballroom Balcony)
9 10 Sudo Equipment
11 12
Sudo Room Servers 13 14 X
Outlets in Room adjacent
to Crow's Nest
15 16 X
X 17 18 Exhaust Fans & Outlets in
over-stage Crow's Nest
X 19 20 Sudo Room outlets
on South Wall


Panel BA

Panel BA

This is a picture of Omni's former panel that was Federal Electric and has since been replaced.

Label -> Breaker # Breaker # <- Label
Ballroom Fans 1 2 Balcony Chandelier (Single)
Ballroom Rafter/Lattice
Disco Ball
3 4 Ballroom Chandeliers
X 5 6
Aux #4 7 8 Panel BAAA (in entrance hall)
X 9 10
Ballroom Rafter/Lattice
Disco Ball Lights
11 12 X
Aux #1 13 14 Aux #2
Aux #5 15 16 Aux #3


Panel BAAA

Panel BAAA
Label -> Breaker # Breaker # <- Label
n/a 2 1 Outlet under counter
(circuit 5 breaker nfg)
n/a 4 3
Outlet (twist lock)
on counter
6 5 Outlet Under Counter
8 7 Outlet next to Counter
(1ft above floor)
& Outlet under counter


This panel used to be under the entrance hall bar counter. When that counter was demolished, this panel was moved to the wall.

Panel C

100amps

I couldn't find this panel to take a picture --yar This panel is camera shy.

Located in Disco Room at base of ladder to DJ booth

Panel D

Panel D

100 amps

This is a picture of something that has since been fixed.